Home Building Budget3/7/2023
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1GENERAL REQUIREMENTS6/7/20238/16/202304080000
7
1.1Plans & Specifications6/7/20238/8/2023036000OpenMedium00
8
1.2Plan Review6/10/20238/9/2023036000OpenMedium00
9
1.3
Permits: Zoning, Building, Environemental
6/10/20238/9/2023036000OpenMedium00
10
1.4Survey6/10/20238/9/2023036000OpenMedium00
11
1.5Impact Fee6/11/20238/12/2023036000OpenMedium00
12
1.6Adminstrative Costs6/12/20238/13/2023036000OpenMedium00
13
1.7Financing Costs6/13/20238/14/2023036000OpenMedium00
14
1.8Legal Fees6/14/20238/15/2023036000OpenMedium00
15
1.9Engineering Fees6/17/20238/16/2023036000OpenMedium00
16
1.10Other6/17/20238/16/2023036000OpenMedium00
17
2SITE PREP8/19/202310/31/202304320000
18
2.1Demolition (Remodel)8/19/202310/18/2023036000OpenMedium00
19
2.2Jacking & Shoring (Remodel)8/20/202310/21/2023036000OpenMedium00
20
2.3
Dust control, Surface Protection
8/21/202310/22/2023036000OpenMedium00
21
2.4Job-Site Access8/22/202310/23/2023036000OpenMedium00
22
2.5Job-Site Security8/23/202310/24/2023036000OpenMedium00
23
2.6Dumpster & Removal8/23/202310/24/2023036000OpenMedium00
24
2.7Clear Lot8/23/202310/24/2023036000OpenMedium00
25
2.8Storage On Site8/26/202310/25/2023036000OpenMedium00
26
2.9Portable Toilet8/27/202310/28/2023036000OpenMedium00
27
2.10Temporary Power8/28/202310/29/2023036000OpenMedium00
28
2.11Temporary Heat8/29/202310/30/2023036000OpenMedium00
29
2.12Scaffolding Rental8/30/202310/31/2023036000OpenMedium00
30
2.13Tool/Equipment Rental8/30/202310/31/2023036000OpenMedium00
31
2.14Other8/30/202310/31/2023036000OpenMedium00
32
3ON-SITE WATER/SEWER11/1/20231/9/202404000000
33
3.1Soil & Perc Tests11/1/20231/2/2024036000OpenMedium00
34
3.2Septic System Design11/4/20231/3/2024036000OpenMedium00
35
3.3
Septic Permits, Inspections, Fees
11/5/20231/6/2024036000OpenMedium00
36
3.4
Septic System Installation, Tie in to House
11/6/20231/7/2024036000OpenMedium00
37
3.5Dewatering (High Water Table)11/6/20231/7/2024036000OpenMedium00
38
3.6
Well, Pump, Trenching, Plumbing to House
11/6/20231/7/2024036000OpenMedium00
39
3.7Well Permits & Fees11/7/20231/8/2024036000OpenMedium00
40
3.8Other11/8/20231/9/2024036000OpenMedium00
41
4UTILITIES7/12/20239/19/202304000000
42
4.1
Town Water: Tap Fees & Hookup
7/12/20239/12/2023036000OpenMedium00
43
4.2
Town Sewer: Tap Fees & Hookup
7/15/20239/13/2023036000OpenMedium00
44
4.3
Electrical: Permit, Connection Fee, Installation
7/15/20239/13/2023036000OpenMedium00
45
4.4
Gas: Permit, Connection Fee, Installation
7/15/20239/13/2023036000OpenMedium00
46
4.5LPN: Tank installation, Hookup7/16/20239/16/2023036000OpenMedium00
47
4.6Oil Tank Installation7/17/20239/17/2023036000OpenMedium00
48
4.7Telecom Hookup7/18/20239/18/2023036000OpenMedium00
49
4.8Other7/19/20239/19/2023036000OpenMedium00
50
5EXCAVATION & EARTHWORK7/22/202310/9/202304640000
51
5.1Cut & Fill7/22/20239/20/2023036000OpenMedium00
52
5.2Blasting7/22/20239/20/2023036000OpenMedium00
53
5.3Removal of Stone/Dirt7/23/20239/23/2023036000OpenMedium00
54
5.4Rough Grading7/24/20239/24/2023036000OpenMedium00
55
5.5Trenching For Utility Hookups7/25/20239/25/2023036000OpenMedium00
56
5.6Foundation Excavation7/26/20239/26/2023036000OpenMedium00
57
5.7Foundation Footing Drains7/29/20239/27/2023036000OpenMedium00
58
5.8Curtain Drains7/29/20239/27/2023036000OpenMedium00
59
5.9Culverts7/29/20239/27/2023036000OpenMedium00
60
5.10Swales7/30/20239/30/2023036000OpenMedium00
61
5.11Retaining Walls7/31/202310/1/2023036000OpenMedium00
62
5.12Ponds8/1/202310/2/2023036000OpenMedium00
63
5.13Other Site Drainage8/2/202310/3/2023036000OpenMedium00
64
5.14Backfill8/5/202310/4/2023036000OpenMedium00
65
5.15Compaction8/5/202310/4/2023036000OpenMedium00
66
5.16Top Soil8/5/202310/4/2023036000OpenMedium00
67
5.17Finish Grading8/6/202310/7/2023036000OpenMedium00
68
5.18Seeding/Sod8/7/202310/8/2023036000OpenMedium00
69
5.19Other8/8/202310/9/2023036000OpenMedium00
70
6FOUNDATION8/12/202310/28/202304480000
71
6.1Footings/Pads8/12/202310/11/2023036000OpenMedium00
72
6.2
Foundation walls/stem walls/grade beams
8/12/202310/11/2023036000OpenMedium00
73
6.3Piers8/12/202310/11/2023036000OpenMedium00
74
6.4
Slabs - Foundation, Basement, Garage
8/13/202310/14/2023036000OpenMedium00
75
6.5Steel Reinforcing8/14/202310/15/2023036000OpenMedium00
76
6.6Anchor Bolts, Hold Downs8/15/202310/16/2023036000OpenMedium00
77
6.7Buikheads8/16/202310/17/2023036000OpenMedium00
78
6.8Sub-Slab Vapor Barrier8/19/202310/18/2023036000OpenMedium00
79
6.9Sump Pump8/19/202310/18/2023036000OpenMedium00
80
6.10Crawlspace Vapor Barrier8/19/202310/18/2023036000OpenMedium00
81
6.11Crawlspace Vents8/20/202310/21/2023036000OpenMedium00
82
6.12Foundation Windows8/21/202310/22/2023036000OpenMedium00
83
6.13Damproofing, Water-proofing8/22/202310/23/2023036000OpenMedium00
84
6.14Foundation Drain Board8/23/202310/24/2023036000OpenMedium00
85
6.15Slab insulation: Edge/Blow8/26/202310/25/2023036000OpenMedium00
86
6.16Exterior Foundation Insulation8/26/202310/25/2023036000OpenMedium00
87
6.17
Exterior Insulation Coating/ Protection
8/26/202310/25/2023036000OpenMedium00
88
6.18Other8/27/202310/28/2023036000OpenMedium00
89
7OTHER MASONRY/PAVING8/29/202311/5/202303920000
90
7.1Patios8/29/202310/30/2023036000OpenMedium00
91
7.2Exterior Stairs8/30/202310/31/2023036000OpenMedium00
92
7.3Masonry Chimneys9/2/202311/1/2023036000OpenMedium00
93
7.4Fireplaces/Hearths9/2/202311/1/2023036000OpenMedium00
94
7.5Driveway9/2/202311/1/2023036000OpenMedium00
95
7.6Walkways9/3/202311/4/2023036000OpenMedium00
96
7.7Other9/4/202311/5/2023036000OpenMedium00
97
8ROUGH FRAMING9/6/202311/18/202304160000
98
8.1Sill & Seal9/6/202311/7/2023036000OpenMedium00
99
8.2
Steel/Wood Carrying Beam, Lolly Columns
9/9/202311/8/2023036000OpenMedium00
100
8.3Floor Framing9/9/202311/8/2023036000OpenMedium00